The Government of Ghana has entered into an Engineering Procurement and Construction (EPC)/Turnkey Project Contract with SINOHYDRO Corporation Limited, a major Chinese dam construction firm of international repute.
Project Implementation Schedule
The key elements of the project schedule are summarized below:
- Commencement of preliminary stage – May 2007
- Commencement of preparatory stage – August 2007
- Construction of basic infrastructure e.g. roads, camps, etc – November 2007
- River Closure – December 2008
- Impoundment of River – June 2011
- Completion and Commissioning – December 2013