Project Implementation

The Government of Ghana has entered into an Engineering Procurement and Construction (EPC)/Turnkey Project Contract with SINOHYDRO Corporation Limited, a major Chinese dam construction firm of international repute.

Project Implementation Schedule

The key elements of the project schedule are summarized below:

  • Commencement of preliminary stage – May 2007
  • Commencement of preparatory stage – August 2007
  • Construction of basic infrastructure e.g. roads, camps, etc – November 2007
  • River Closure – December 2008
  • Impoundment of River – June 2011
  • Completion and Commissioning – December 2013